Exterior Re-Painting

Planned Start Date: 4/8/24

Completion Date: 7/15/24

Status: Completed

The exteriors of our homes are reaching the end of their useful life and need to be repainted.

This is a large project which will take 2-3 months. This project will have some impact on daily life at Galewood Circle. The painting company will be placing a portable toilet and storage container in one of our guest parking areas. Vehicles will be regularly entering, parking and exiting. Note: home colors will NOT change. The last re-painting project was completed in 2013. As part of this project, we will also be checking the accuracy of the paint colors currently in our Architectural Standards document.

If you’d like to have additional prep work done on your property before the painting begins, such as removal of old alarms, doorbells, etc; stucco work; carpentry, please complete this form.

Painting Schedule

Week 1: April 8-17 100, 102, 104, 106, 108, 110, 112

Week 2: April 15-April 24 114, 116, 118, 120, 122, 124, 126

Week 3: April 22-May 1 128, 130, 132, 134, 136, 144, 146

Week 4: April 29-May 8 148, 150, 152, 154, 156, 158, 160

Week 5: May 6-May 15 162, 164, 166,168, 170, 172, 174

Week 6: May 13-May 22 176,178, 180,182,184, 186,188

Week 7: May 20-May 29 101, 103, 111, 113, 117, 119, 121

Week 8: May 27-June 5 123, 125, 129, 133, 135, 137, 139

Week 9: June 3-June 12 141, 143, 151, 153, 155, 163, 165

Week 10: June 10-June 19 179, 181, 183, 185, 187, 189, 200

Week 11: June 17-June 26 202, 204, 206, 208, 210, 212, 214,216